The marine-grade lumber for our 4 new bridges and 2 retaining walls began arriving on site today. Our contractor began working on the wall in front of #8 green this week.
Below is a photo of the 36+ year old corrugated metal pipe being removed under the cart path from #17 to #18. This 48" diameter pipe will be replaced with a new HDPE pipe (see the after picture below)